Delayed and never started lines according to the Istanbul rail system investment program

Delayed and never started lines according to the Istanbul rail system investment program
Delayed Lines by Rail System Investment Program: 57.46 km

KadıköyEagle: (21.66 km) It was going to end in 2011. It's not over on time.

Bagcilar-Olympic: (15.8 km) 2012 would end in the middle. Still waiting for the opening.

Üsküdar-Çekmeköy: (20 km) 2013 is planned to be finished.

According to the Rail System Investment Program Lines that Never Start: 51,5 km.

Ataşehir-Monoray: (11 km). 2012, and 2013 will be finished. Why didn't it start.

Besiktas-Giyimkent-Bağcılar: (24.5 km) 2012 began in the middle, and will end at the beginning of the 2015.

Bakirkoy-Beylikdiuzu (25 km) 2013 start and 2015 also finished.

Bakirkoy-Bagcilar: (9 km). He would start at the beginning of 2013 and finish at 2014.

Yenikapı Bakırköy: (7 km) 2013 should start at the beginning. Because it's planned to end at 2015.

Ünalan-Mecidiyeköy (11,8 km) planned to be built between 2014 UM 2015. No work involved in planning.