Work on the 11 Level Crossing Project in Malatya

The Republic of Turkey State Railways TCDD 5. Regional Directorate of Malatya central and districts at various points 11 level crossing project work continues.

In total, 85 million TL estimated cost of the projects, except Dilek Göçmen Yolu and Doğanşehir Polatköy other 9 project drawing works will be completed within this year, said construction work will begin.

State Railways 5. According to the data of Regional Directorate, the project completed Hekimhan Güzelyurt, Malatya Fethiye, Malatya Yazihan, Yazihan Surur Village, Yesiltepe Samankoy, Topsogut Village Road, Battalgazi Kemerköprü road, Battalgazi Garden Road will begin construction of level crossings.

At the level crossing project in Dilek Yaka Village, the end was approached. The physical realization rate of the project was recorded as 90.

Source : www.yenimalatya.com.t is