The first stage of the Üçyol-Üçkuyular Metro started test drives between İzmirspor and Hatay stations

Izmir Metropolitan Municipality Mayor Aziz Kocaoğlu'nun recently participated in a television program 'suddenly can open' the trip of the Üçyol-Üçkuyular Metro, which forms the first stage of Izmirspor and Hatay travel tester between the passengers began traveling. With the participation of CHP leader Kemal Kılıçdaroğlu in recent months, the Metropolitan Municipality opened the Ege University Hospital-Bornova Evka 3 Metro Line and started to make the finishing touches on this line of 1.5. Municipal authorities, the test trips in Bornova 23 week between Izmirspor and Hatay stations between the 1.5 kilometer line test runs will take longer, the results will be determined by the passenger voyage, he said.
BASIC BAYKAL ATTI
In 2005, the light appeared on the Üçyol-Üçkuyular Metro Line, which was laid the foundation of the period by CHP Chairman Deniz Baykal, but the contracting firms did not comply with the specifications, and that the contracts were terminated. After nearly 7 years of construction work, the total length of the 5.5 kilomletreyi line, although not all of the 1.5 kilometer section covering Izmirspor and Hatay stations began to countdown.
SET, TUNNEL INDI
In the last week, even the downloaded subway set started between Izmirspor and Hatay. The municipal authorities stated that all kinds of work in the stations and tunnels ended, and that the train set had started without passengers on the line. The train set on the line as the progress of the railway station, especially between the railway station and indicating that there is a friction between the authorities, the passengers will start the test journey with the completion of the trial voyages said.
Step by step metro
* The first auction took place at the March 2005. Bayındır Construction company 90 won the tender for million 898 million 248 thousand TL.
* 2 In June, Deniz Baykal in 2005, with Transportation Minister Binali Yildirim as the base. The line is expected to be completed at 24 per month at 2 June 2007.
* The first digging was hit at 5 July 2005.
* 14 On February 2006, Metropolitan Municipality has appealed to Bayındır İnşaat.
* In November 2006 the tender was canceled.
* 23 January 2007'de auctioned for the second time.
* 3 April 2007'da Bozoğlu received the tender.
* Due to the appeals, the contract with Bozoglu could only be signed in May.
* 31 2008 with 15 monthly time extension for 2010 in October XNUMX is January.
* However, when Bozoğlu Construction stopped the work, 2009 13 annulled its contract with this company in August and started the new tender process.
* By dividing the project and deciding to tender, Metropolitan Municipality, 5 has made a tender for the Izmirspor and Hatay stations which formed the first stage in October.
* OZTAS Company received the business.
* For the completion of the job, the 510 daily schedule was envisaged. However, the time has come until now with extensions.

Source: New Asir

Similar Railway News

Similar High Speed ​​Train News

About Levent Ozen
Every year, high-speed rail sector, the European leader in the growing Turkey. Investments in railways, which take this speed from high-speed trains, continue to increase. In addition, with the investments made for transportation in the city, the stars of many of our companies making domestic production shine. It is proud that Turkish high-speed tren national train ”production has been started in addition to the companies producing domestic tram, light rail and subway vehicles. We are very happy to be in this proud table.

Be the first to comment

Comments

This site uses Akismet to reduce spam. Learn how your comment is processed.