97 Bored Piles Driven for Darica Osmangazi Bridge

Pieces of Bored Pile Driven for Darica Osmangazi Bridge
97 Bored Piles Driven for Darica Osmangazi Bridge

Existing Osmangazi Bridge bored pile concrete productions are carried out in Darica. 205,85 bored piles will be driven for the 7 meter long 97 span bridge. With the additional bridge built by Kocaeli Metropolitan Municipality, access to Aşiroğlu Street and the industrial areas in the region will be made safer and more comfortable. As part of the project, the intersections will be renewed.

BRIDGES AND CONNECTION ROADS

Within the scope of Darıca Osmangazi Bridge Replication and Connection Roads Construction Work, the connection road of Aşiroğlu Street and Osmangazi Tunnel Junction on the D-100 Highway will be turned into a 2×2 road. Marmaray Osmangazi Train Station will be crossed by a bridge over the TCDD line. Within the scope of the works, a 205,85-span bridge with a length of 7 meters and connection roads with a length of 1.280 meters will be built. In addition, 342 meters of earthen wall, drinking water, waste water and rain water lines, pavement and parquet works will be done.

NEW ROAD AND PEDESTRIAN WAYS

1.030 cubic meters of prestressed beams and 1.255 tons of ribbed iron will be used for Darica Osmangazi Bridge Replication and Access Roads. For the connection roads, 3 tons of PMT, 500 tons of PMAT, 2.500 tons of binder, 1.550 tons of bituminous foundation, 1.975 tons of abrasion asphalt will be laid. For the pedestrian sidewalks, 1.235 thousand square meters of parquet, 3 thousand 2 meters of borders and 350 thousand 2 meters of median borders will be manufactured.