Within the scope of Kuruçeşme Tram Line Project, the existing Akçaray Tram Line will be connected to Kuruçeşme by passing from Plajyolu Station to the opposite side of the D-100 upon completion of the works. The legs of the tram overpass bridge, which is 290 meters long, with 9 legs and 8 spans, which will provide the tramway, are rising.

COLUMN AND FOUNDATION MANUFACTURING IS DONE

The production of 100 bored piles for the piers of the 290-meter-long bridge that will connect the Akçaray Tram Line to Kuruçeşme via the D-130 was completed at the beginning of January. The production of columns, foundations and head beams continues in the works carried out by the Kocaeli Metropolitan Municipality teams for the construction of the bridge piers. With the work done, your feet started to appear, and rainwater production continues in the project. Two new modern pedestrian overpasses were previously offered to the citizens in the project, where the work continued despite the harsh weather conditions.

TRAM LINE WILL REACH 23,4 KILOMETERS

With the completion of the Kuruçeşme tram line, the length of the Akçaray tram line will reach a double line of 10 thousand 212 meters. The single-line length of the tram will reach 3 kilometers, with a 23,4-kilometer single-line warehouse area. With Kuruçeşme station, the number of stops will increase to 16. With the project, which will add convenience and value to the lives of citizens, access to Izmit center, Sekapark and Izmit Bus Station will be easier.

Be the first to comment

Leave a response

Your email address will not be published.


*