The frequency and duration of the interruptions have decreased in the places where investments were made to increase the energy quality, meet the power demands and create alternative lines in the interruptions. SEDAŞ carries out its mission of güvenli ensuring sustainable access of customers to safe, high quality, reliable electric energy with investments S.

SEDAŞ continues its investments in the region with big projects. The projects completed by SEDAŞ in Kocaeli make a difference in energy quality and reduce the number of times and durations. The alternative lines also facilitate quick interventions in faults. In order to meet the power demands of SEDAŞ, the new 34,5 KV distribution connection lines of the downloading centers of TEİAŞ are also formed.

SEDAŞ'S GREAT PROJECTS

TRAMVAY GÜZERGAHI AG-OG UNDERGROUND CABLE ELECTRICAL DISTRIBUTION NETWORK PROJECT
SEDAŞ, completing the low and medium voltage underground network investment along the tram route, is connected to the Gölcük I and Gölcük II exits, departing from the distribution center next to the train station and being fed from the İzmit Substation. and a part of the underground cable network under the high-speed railroad, a large plant investment work, and the Central Bank and the in-house distribution center between the 100 km completely renewed the route. Instead of the existing hair kiosks dividing the energy line under the Carrefour Bridge, 2 new concrete mansion transformer building cabin was installed and the Gölcük I and Gölcük II circuits were entered into separate cabins and an alternative energy distribution line was created for the rapid interruption between these outputs.

IZMIT 380 DOWNLOAD CENTER 100 KM CONNECTION LINE INVESTMENT PROJECT
In order to meet the rapidly increasing electricity demand, to reduce the load on the energy transmission lines, and to ensure the security of the system. investment and distribution lines brought to the city. 380 mileage excavation and 154 thousand meters underground cable electrical connection line was installed.
Kocaeli Substation was the third and biggest download center in Izmit. SEDAŞ has ensured the introduction of this big project with its connection lines. With the investment of the new underground cable power pipeline, SEDAŞ has created the opportunity to buy electricity from the Kaynarca, from Köşeköy, Izmit, Gölcük and Kandıra, to the new Transformer Substation of Kocaeli. With the connection lines made by SEDAŞ, the energy demands that will be needed by the factories to be established in the Organized Industrial Zones of Asım Kibar and Ali Kahya can be met. TEIAS was connected to 100 circuit output city networks from Izmit 380 KV Transformer Substation. With these connections, Yahya Kaptan region, Gundogdu permanent residences, Kocaeli University Hospital, Izmit Industrial Zone, Yenisehir neighborhood, Governorate, Real Mall, Kocas, Goodyear factory, Mobesko, Pakmaya factory, Knauf factory, including Izmit District in approximately 8 3 part, Kandıra district F-Type Prison up to the section and Kartepe Hacıhalim neighborhood, Station district, Köseköy industrial site, such as energized, more continuous and high-quality energy for a great investment has been completed.

CONNECTION PROJECT OF KARTEPE AND ARSLANBEY TRANSFORMER CENTER AND ENVIRONMENTAL LINES
In the project of environmental connection lines, which was established by TEİAŞ and which was established for the feeding of the city network, the energy feeder output of 2 was allocated and alternative feeding points were created. An alternative to Köseköy TM, which is currently in the supply of Arslanbey, has been created and approximately 2,1 km excavation has been carried out on the route determined for underground cable electricity network and a total of 7 km medium voltage underground network has been established.

OTHER PROJECTS OF SEDAŞ
Besides the connection lines of the transformer downloading centers in the major projects of SEDAŞ, large projects were completed in different districts of Kocaeli.

BAŞİSKELE DISTRIBUTION CENTER İZMİT CONNECTION LINE PROJECT
Low and medium voltage underground cable energy distribution lines were installed in the 5,5 kilometer area between the Sefa Sirmen Boulevard Başiskele Electricity Distribution Center and Yuvacık turnoff. Başiskele region, where the construction of the former Gölcük road has increased, has had the opportunity to be energized from the İzmit substation. First of all, the whole Yuvacık region and the Seymen area can now be energized from this line. The Medium Voltage network, which has completed its economic life in İzmit Bay Industrial Zone, was renewed and it was taken to the underground. The existing 5 units of open switchgear on the industrial site were renewed and converted into a modular system. The Medium Voltage network that passes through the plane trees on the old Gölcük road and which has a problem with breakdown intervention and which has a safety distance problem has been taken to the underground. 5 Distribution center was built and additional exits were provided to the regions where industrialization was intense.

İZMİT I-II ENH UNDERGROUND NETWORK PROJECT
1 of the project. stage, Yahya Kaptan AYM3 Distribution Center and Kandıra Crossroad were taken to the underground between Zikri Soyer Distribution Centers. 1,5 km excavation was performed on the total route. In addition to Zikri Soyer Distribution Centers, along with the Distribution Transformer Substation, arrangements were made in the low-voltage network in the vicinity of the Democracy Boulevard to meet the additional power demands. The lines energized from Köseköy Transformer Center feed the regions such as İzmit Industrial Zone, Yenişehir neighborhood, Governorship, Real Shopping Mall, Koçtaş, Goodyear Factory, Mobesko, Pakmaya Factory, Knauf Factory, Kartepe Hacıhalim District, İstasyon District and Köseköy Industrial Site.

KÖRFEZ, HEREKE KIŞLADÜZÜ LOCATION UNDERGROUND AG + MV + LIGHTING PROJECT
Nuh I-II 477 conductive medium voltage line passing through the Hereke Kisladuzu neighborhood was completely underground between the entrance and exit of the neighborhood. Within the scope of the project, 5 km medium voltage, 3 km low voltage and 3 mileage network were installed. 80 9 meters of steel galvanized lighting poles and 56 pieces of field power distribution boxes for subscriber feedings were installed in the region for illumination.

DERİNCE CUMHURİYET CAD. (DENİZCİLER CAD.AG/YG LIGHTING UNDERGROUND PLANT PROJECT
Final Stop The 400 kVA transformer in the cabin was disassembled and power increased to 630 kVA. Dumlupınar District and Republic and Rıhtım Street in the project on the work of the existing overhead lines to take the ground, modular cell Lawn Carpet, Swan transformer buildings, the entrance and exit operations were made and Necatibey Building open type cells modular transformation was performed. 3 new Transformer concrete kiosk cabin building was installed in order to provide the power demands to be met in the region. In general, 4,8 km Medium voltage, 6,2 km Low voltage, 5,9 km lighting network was installed. 117 pcs 9 meter steel galvanized lighting pole, 81 units were installed in the field electrical distribution box.

KOCAELI, GEBZE, MUSTAFAPASA MAH., YILMAZ ARGON STREET, UNDERGROUND AG + MV and LIGHTING NETWORK PROJECT
Gebze District, Mustafapasa District, Yilmaz Argon Street in the work of the city network to take the underground, 1,7 km was taken to the underground. The existing 2 concrete pavilion was replaced by new concrete pavilions with 1000 kVA and 630 kVA transformers. 44 new lighting poles were installed within the scope of the project. Approximately 8,3 km low voltage and 6,6 km medium voltage network were installed for underground cable distribution network.

SEDAŞ's studies are only part of their investments. Every day, SEDAŞ is sewing directly to meet the electrical connection demands of the new buildings with small additional installation works for electrical connection and draws conductors to these poles for connection and then carries out energy connection works.