Work on Akçaray Tram Project 7 / 24 continues: The works of Akçaray tram project, which is still being built by Kocaeli Metropolitan Municipality, continue without any day or night. Within the scope of the project, studies were carried out at different points throughout the night.

RAIL MOUNTED

Tramway works continued until the first lights of the morning. In this context, rail assembly and concrete throwing were carried out at Şahabettin Bilgisu Street, Gar district and warehouse area. Accordingly, 40 meters in Şahabettin Bilgisu Street, 50 meters in the Gar area and 40 meters in the storage area were installed. In the early hours of the morning after the installation of the rail assembly, concrete was thrown in the regions.

KATANER POLE STRIPS

On the one hand, the rail line is also on the tram line and the sewing of the kataner poles continues. Starting from the East Barracks Park to the Thursday Market area, the 6 pieces of kataner pole were planted.

WELDING AND WIRING

The gaps between the rails along the tram line were welded. In addition, the 350 section of the area between the East Barracks Park and Thursday Market was cut.

Be the first to comment

Leave a response

Your email address will not be published.


*