50 meter rail, 100 meter infrastructure per day on bus station-Sekapark line

50 meter rail and 100 meter infrastructure in the Otogar-Sekapark line: Rail laying and infrastructure arrangement works for the tram line of Otogar-Sekapark, which was started by Kocaeli Metropolitan Municipality, continue intensively. 50 meter rail is installed per day, the infrastructure works are carried out at the 100 meter.

YAHYA KAPTAN 15 JUNE
In the Yahya Kaptan region, where the most intensive work is being carried out, it was announced that the flooring work will be completed by 15 June. 50 meter rail laying process will be done on the day of departure and arrival, the infrastructure will be transitioned to the ending regions. After 10 days, Rafet Karacan Boulevard and 20 days will be started at Gazi Mustafa Kemal Boulevard.

INVESTMENT IN THE FUTURE
Due to the operation of the tramway, infrastructures along the length of the route change. In the area between M.Alipaşa-Kandıra junction, the 4 team is doing 100 meter infrastructure renewal per day. While ISU, Sedaş, Telekom and İzgaz are working in coordination, the city's 30-50 is invested in infrastructure after years. Meanwhile, Sekapark of the tram line was started working for further extension of 2 miles until the end.

Similar Railway News

Similar High Speed ​​Train News

About Levent Ozen
Every year, high-speed rail sector, the European leader in the growing Turkey. Investments in railways, which take this speed from high-speed trains, continue to increase. In addition, with the investments made for transportation in the city, the stars of many of our companies making domestic production shine. It is proud that Turkish high-speed tren national train ”production has been started in addition to the companies producing domestic tram, light rail and subway vehicles. We are very happy to be in this proud table.

Be the first to comment

Comments

This site uses Akismet to reduce spam. Learn how your comment is processed.