Çorum railway project among our commitments

Çorum railway project commitments: 1 2015 285 General Election Declaration, Samsun-Çorum-Kırıkkale-Ankara freight and passenger train line will be made in the form of expressing Uslu, rail and freight and passenger line that will allow transportation XNUMX km. and that the tender process for the project continues.

AK Party Deputy Corum, Grand National Assembly Administration Salim Uslu, the fast-train project is not in the AK Party Election Declaration by responding to the claims, the party election declaration "Transportation and Logistics" section, 176. ı Samsun-Çorum-Kırıkkale-Ankara ğ will continue to make high-speed train lines that will carry cargo and passengers ale, he said.

In the election declaration, Salim Uslu explained that şu Çorum Railway, is clearly mentioned and also lar We will integrate our railway network, which we will create up to our borders in a way to allow freight and passenger transportation by rail, to the international system e.

Kırıkkale-Çorum-Samsun Railway Project (285 Km.):
Thanks to the planned project, Ankara - Çorum - Samsun will turn into a short distance and high standard line.

This new project, the ongoing construction work of the Ankara - Yerkoy railway line 112. It is a railway line which departs from Çorum - Merzifon - Samsun direction. Ankara - Samsun line approximately 400 Km. It will be.

In addition, a connection line which departs from Merzifon station and provides connection to Amasya - Turhal - Tokat has been realized within the scope of this study.

The preliminary project and feasibility study was tendered on 26.08.2010 and completed on 10.06.2013.

The implementation of this line, which is planned to be projected according to 250 km / h speed with double-line electrical signal, has been included in the investment program of 2015 for 10 Million TL.

The project work was planned as 3 cuts in Delice-Çorum, Çorum-Merzifon and Merzifon-Samsun.

Delice-Çorum Railway Survey Project, Engineering and Consultancy Service Procurement tender was held on 9 June.

Çorum-Merzifon Railway Survey Project, Engineering and Consultancy Service Procurement tender was held in September by the General Directorate of TCDD. The procurement process continues. İhale