Yeni Mahalle-Şentepe The moment of decision in the cable car (PRIVATE NEWS)

The moment of decision on the ropeway: Anakent Mayor Melih Gökçek has reached a new stage in the ropeway projects he insisted on despite all objections. According to the information obtained from the Republic of Ankara, priority was given to the Yenimahalle-Şentepe line in the ropeway projects, while the Siteler-Karapürçek line is currently frozen. According to the results of the bargaining of the Şentepe line, it is noted that the Sites can be continued or the tender can be canceled.

Reducing costs

In the second phase of the tender which was canceled previously, only Italian Leitner AG SpA offered a bid. German
Doppelmayr Seilbahnen did not continue this project. Anakent Municipality EGO General Directorate Rail Systems Department carries out the negotiations with the Italian company.

According to the developments in the line, the German firm wants to maintain the position on the Siteler line.
The fact that there is a double difference between the estimated price and the official offer in the ropeway projects is stated to be due to the project details.
According to the information obtained, companies in the projects that occur after the estimated cost of majestic station buildings cost
Upgraded. In the second phase, cost reduction measures are taken in the project of Şentepe line. The new negotiations will be evaluated in this context,
It was learned that the municipality of Anakent wanted to make a decision in the 1 month and to ensure the construction phase.

In case of reconciliation, place delivery will be made in 10 days, the project will be completed in 480 days.
In the case of realization of the cable car passenger transport will be the first in Europe.
Passenger transport is not allowed However, passengers can be transported by cable car in Brazil and South Africa.

Source : Rayhaber