Tram Works at Bursa Altıparmak Street to Start in November

Construction works of Bursa Metropolitan Municipality's 6.5 kilometer Sculpture-Garage Tram Line continue. The Darmstad Street section of the line, which started its construction at the beginning of August and started construction works on Stadium Street, began recently.

As the paving of the first phase of the stadium ended, the laying of the railings began in the scope of Darmstad Street works.

Until the 20 day, Darmstad Street works will be completed and planned to pass to Altiparmak Street in early November. The work at Altıparmak Street is planned to be completed in December, within the month of 1,5.

Source: WOWTURKEY