50 meter rail, 100 meter infrastructure per day on bus station-Sekapark line

50 meter rail and 100 meter infrastructure in the Otogar-Sekapark line: Rail laying and infrastructure arrangement works for the tram line of Otogar-Sekapark, which was started by Kocaeli Metropolitan Municipality, continue intensively. 50 meter rail is installed per day, the infrastructure works are carried out at the 100 meter.

YAHYA KAPTAN 15 JUNE
In the Yahya Kaptan region, where the most intensive work is being carried out, it was announced that the flooring work will be completed by 15 June. 50 meter rail laying process will be done on the day of departure and arrival, the infrastructure will be transitioned to the ending regions. After 10 days, Rafet Karacan Boulevard and 20 days will be started at Gazi Mustafa Kemal Boulevard.

INVESTMENT IN THE FUTURE
Due to the operation of the tramway, infrastructures along the length of the route change. In the area between M.Alipaşa-Kandıra junction, the 4 team is doing 100 meter infrastructure renewal per day. While ISU, Sedaş, Telekom and İzgaz are working in coordination, the city's 30-50 is invested in infrastructure after years. Meanwhile, Sekapark of the tram line was started working for further extension of 2 miles until the end.

Be the first to comment

Leave a response

Your email address will not be published.


*